GB ARCHON 2913 GLG-03-02-73 · Item · 19 July 1994
Part of Guild of Our Lady of Grace / Meryemana

Vestry scheme will take three months from instructions to proceed.
Borough's letter not specific but they have declared an intent to address the drainage problem. Suggest instruct to go ahead and inform IHCT and Borough that you have done so on the basis of their letters. Need to meet you and Mr Mellamphy to finalise the brief so can start on the drawings

Basil and David Hatcher
GB ARCHON 2913 GLG-03-02-36 · Item · 3 December 1991
Part of Guild of Our Lady of Grace / Meryemana

Referring to the English Heritage letter to James Hall (IHCT). It is clear that additional work and drawings need ot be done - particularly on pew storage and toilets. ".. appalled at the time this has taken..." Suggest joint meeting with Dr Heley and Mr Mellamphy.
Includes his response to IHCT.

Basil and David Hatcher
GB ARCHON 2913 GLG-03-02-23 · Item · 12 February 1991
Part of Guild of Our Lady of Grace / Meryemana

Meeting with Church Advisory Board for Redundant Churches, The Borough, IHCT and Meryemana Foundation - did not get the necessary assurances regarding pew removal. Borough Planning Officers - need a change of use if the vestry is to become a caretaker's flat - lists alterations which will attract need for Listed Building consent. Work (more than expected) done so far requires payment and a review of brief

Basil and David Hatcher
GB ARCHON 2913 GLG-03-02-26 · Item · 19 June 1991
Part of Guild of Our Lady of Grace / Meryemana

Discussed plans with Mr Mellamphy - only one disabled toilet required - plans acceptable. Stairway to bell-ringers floor impractical - will be excluded. Drawing enclosed for Vestry/Caretaker accommodation. Application to the Borough for Listed Building application for the Vestry, Toilets, Pew removal; and change of use for vestry to living accommodation. Mr Mellamphy is going away for a few weeks.

Basil and David Hatcher
GB ARCHON 2913 GLG-03-02-20 · Item · 12 October 1990
Part of Guild of Our Lady of Grace / Meryemana

Discussing with Mr Mellamphy, recommendation that plans for Vestry etc. are discussed with English Heritage and Ipswich Chief Planning Officer before going to far. Includes a schedule of hourly rates.
As a member of ICHT he informs that both phases of external repairs are to start in early Spring 1991 and will include re-roofing the vestry

Basil and David Hatcher
GB ARCHON 2913 GLG-03-02-66 · Item · 3 March 1994
Part of Guild of Our Lady of Grace / Meryemana

Sufficient work to enable the Vestry to be used for meetings. Need to agree the lease with IHCT before incurring too much cost. Ready to discuss with the planners but the proposals need the blessing of the IHCT and English Heritage. Look to the future and phase 2 or 3 if possible

Basil and David Hatcher
GB ARCHON 2913 GLG-03-02-79 · Item · 8 December 1994
Part of Guild of Our Lady of Grace / Meryemana

Writing about end of the St Nicholas Project; obsessed with the building; lost momentum and credibility.
However, if St Mary Elms should be considered for redundancy / shared use then the Guild would be interested - it's the one they'd chose to re-establish the shrine of Our Lady of Grace.

Heley, Margaret Mary (Maire) Dr (1930-2020)